Ausenco awarded $53 Million contract to manage underground, surface infrastructure construction and coal preparation plant upgrade work for the Kestrel Joint Venture. Kramer Ausenco provided project engineering services during the procurement, construction, commissioning and handover for Kestrel Mine Extension. The extension is 7km southeast of the existing Kestrel Mine site. It has its own Mine Infrastructure Area, with two portals to the underground pit. Production is 5.7M Tonnes/year.
- Project
- Kestrel Mine Extension
- Location
- North east of Emerald, Central Queensland
- Client
- Rio Tinto Coal Australia
- Project Type
- Resources
- Year Completed
- 2012
Related Documents
-
Kestrel Mine Extension
312 kB